Nearing completion of my rebuild I look back on the project and realise I could have done several things better or smarter.
I know you have all seen this kind of advice before, and I had also, but some points I did not really take literally enough. So here are a few things that might help someone else:
1) Do not sell or discard ANYTHING until the car is finished.
I sold off a perfect windshield frame as I had two, but I had not removed the rubber seal from the base of the one I kept, and there was rust underneath. It cost more to repair that rust than I was paid for the good frame I sold!
2) Labels for ziploc bags of parts are best written on paper and put inside the bag, Much easier to read than marker on masking tape on the outside. Describe the items in as much detail as possible, NOT "rack mount bolts" (steering rack or luggage rack) NOT "interior miscellaneouis", there is no part of your car that is "miscellaneous". Two years later it is sometimes tough to identify things.
3) Buy mounting hardware kits from your parts supplier instead of buying the bits separately; it may be cheaper, you will certainly have tyhe correct fasteners.
4) Try to keep the garage and parts inventory as organised as possible (something I'm not good at) as it can save a lot of time not having to look for stuff.
5)Be patient in selecting a painter. You will be amazed at the range of prices you will be quoted when asking for the same job on the same car.
It is important you have the painter inspect the car carefully and discuss in deatail what you want done, and how soon you expect the work completed.
If the shop does collision work they may charge a lower rate to work on your car during slower times, but if you are paying the regular shop rate you should expect your job to have the same priority as the other work, and be finished in a few weeks. (If extra work that wasn't originally obvious, like hidden rust, becomes necessary, you will have to be prepared to pay extra, or your job will be put aside in favour of more profitable work.)
Hope this helps a few people to keep projects on track.
Simon.
I know you have all seen this kind of advice before, and I had also, but some points I did not really take literally enough. So here are a few things that might help someone else:
1) Do not sell or discard ANYTHING until the car is finished.
I sold off a perfect windshield frame as I had two, but I had not removed the rubber seal from the base of the one I kept, and there was rust underneath. It cost more to repair that rust than I was paid for the good frame I sold!
2) Labels for ziploc bags of parts are best written on paper and put inside the bag, Much easier to read than marker on masking tape on the outside. Describe the items in as much detail as possible, NOT "rack mount bolts" (steering rack or luggage rack) NOT "interior miscellaneouis", there is no part of your car that is "miscellaneous". Two years later it is sometimes tough to identify things.
3) Buy mounting hardware kits from your parts supplier instead of buying the bits separately; it may be cheaper, you will certainly have tyhe correct fasteners.
4) Try to keep the garage and parts inventory as organised as possible (something I'm not good at) as it can save a lot of time not having to look for stuff.
5)Be patient in selecting a painter. You will be amazed at the range of prices you will be quoted when asking for the same job on the same car.
It is important you have the painter inspect the car carefully and discuss in deatail what you want done, and how soon you expect the work completed.
If the shop does collision work they may charge a lower rate to work on your car during slower times, but if you are paying the regular shop rate you should expect your job to have the same priority as the other work, and be finished in a few weeks. (If extra work that wasn't originally obvious, like hidden rust, becomes necessary, you will have to be prepared to pay extra, or your job will be put aside in favour of more profitable work.)
Hope this helps a few people to keep projects on track.
Simon.